Browsing articles tagged with " Traffic"
Updated: Jul 11, 2012
There are: No Comments

Additional Lane at St. Patrick’s Church Roundabout Rochestown Road

 

Some months ago that we were informed that the money had been allocated to upgrade and make provision for an extra lane on the above roundabout and I contacted officials to find out what the exact position is in relation to this work.  The Divisional Manager has now responded informing me that Land acquisition is underway. We hope to be on the ground and providing the additional lane this year.  The project is being actioned by the Roads directorate.

 

 

Updated: Nov 15, 2011
There are: No Comments

Latest Update for N25 Bandon/Sarsfield Road Interchanges

Night time works are planned over the remaining nights of this week in the Sarsfield Road area. A number of service ducts are to be installed under the existing Sarsfield Road both north and south of the roundabout to facilitate the installation of new services. Obviously the works are being carried out at night in order to minimise disruption to traffic.
Over the coming weeks the works will continue to be concentrated in two main areas as follows:

Updated: Sep 30, 2011
There are: No Comments

N25 Update

I am pleased to report that further progress has been made at a pace on this project.  Does anyone else notice how bright the area looks now that all the shrubbery and trees have been removed.  Though it is policy of council to preserve trees where possible however in the name of progress some will have to give way for the greater good. Earthworks in the Bandon Road Roundabout centre island will be continuing for a number of weeks and will
necessitate a number of traffic movements from the roundabout circulating carriageway into the roundabout
centre island itself. Motorists using the roundabout are asked to pay particular attention to roadwork signage
over the coming period and to take due care in relation to construction traffic in the roundabout area. Lane
closures either on the roundabout or on the roundabout approaches are not anticipated over the coming
period.
From a structures point of view the columns at the western side of the Bandon Road Roundabout will be
progressed over the coming weeks and progress here will be readily apparent to motorists using the
roundabout. Construction of the reinforced earth panel wall west of the Bandon Road Roundabout will get
underway before the middle of October and the first concrete pour associated with the proposed structure at
the eastern side of the Bandon Road Roundabout is also scheduled before the middle of October. It is
currently anticipated that at least some of the bridge beams on the western structure at Bandon Road
Roundabout may be in place before Christmas.
Significant earthworks are also continuing in the area south of the existing N25 between Bandon Road
Roundabout and Sarsfield Road Roundabout. Works in this area are scheduled to continue for a number of
months as part of the construction of a dedicated westbound link road parallel to the N25 mainline in this
area.
Plans for demolition of the existing footbridge at Sarsfield Road Roundabout and demolition of the existing
footbridge east of Bandon Road Roundabout are being advanced and a further update will issue under this
heading during week commencing Monday 2nd October 2011.
Earthworks in the Bandon Road Roundabout centre island will be continuing for a number of weeks and will
necessitate a number of traffic movements from the roundabout circulating carriageway into the roundabout
centre island itself. Motorists using the roundabout are asked to pay particular attention to roadwork signage
over the coming period and to take due care in relation to construction traffic in the roundabout area. Lane
closures either on the roundabout or on the roundabout approaches are not anticipated over the coming
period.
From a structures point of view the columns at the western side of the Bandon Road Roundabout will be
progressed over the coming weeks and progress here will be readily apparent to motorists using the
roundabout. Construction of the reinforced earth panel wall west of the Bandon Road Roundabout will get
underway before the middle of October and the first concrete pour associated with the proposed structure at
the eastern side of the Bandon Road Roundabout is also scheduled before the middle of October. It is
currently anticipated that at least some of the bridge beams on the western structure at Bandon Road
Roundabout may be in place before Christmas.
Significant earthworks are also continuing in the area south of the existing N25 between Bandon Road
Roundabout and Sarsfield Road Roundabout. Works in this area are scheduled to continue for a number of
months as part of the construction of a dedicated westbound link road parallel to the N25 mainline in this
area.
Plans for demolition of the existing footbridge at Sarsfield Road Roundabout and demolition of the existing
footbridge east of Bandon Road Roundabout are being advanced and a further update will issue under this
heading during week commencing Monday 2nd October 2011.
Earthworks in the Bandon Road Roundabout centre island will be continuing for a number of weeks and will
necessitate a number of traffic movements from the roundabout circulating carriageway into the roundabout
centre island itself. Motorists using the roundabout are asked to pay particular attention to roadwork signage
over the coming period and to take due care in relation to construction traffic in the roundabout area. Lane
closures either on the roundabout or on the roundabout approaches are not anticipated over the coming
period.
From a structures point of view the columns at the western side of the Bandon Road Roundabout will be
progressed over the coming weeks and progress here will be readily apparent to motorists using the
roundabout. Construction of the reinforced earth panel wall west of the Bandon Road Roundabout will get
underway before the middle of October and the first concrete pour associated with the proposed structure at
the eastern side of the Bandon Road Roundabout is also scheduled before the middle of October. It is
currently anticipated that at least some of the bridge beams on the western structure at Bandon Road
Roundabout may be in place before Christmas.
Significant earthworks are also continuing in the area south of the existing N25 between Bandon Road
Roundabout and Sarsfield Road Roundabout. Works in this area are scheduled to continue for a number of
months as part of the construction of a dedicated westbound link road parallel to the N25 mainline in this
area.
Plans for demolition of the existing footbridge at Sarsfield Road Roundabout and demolition of the existing
footbridge east of Bandon Road Roundabout are being advanced and a further update will issue under this
heading during week commencing Monday 2nd October 2011.
Earthworks in the Bandon Road Roundabout centre island will be continuing for a number of weeks and will
necessitate a number of traffic movements from the roundabout circulating carriageway into the roundabout
centre island itself. Motorists using the roundabout are asked to pay particular attention to roadwork signage
over the coming period and to take due care in relation to construction traffic in the roundabout area. Lane
closures either on the roundabout or on the roundabout approaches are not anticipated over the coming
period.
From a structures point of view the columns at the western side of the Bandon Road Roundabout will be
progressed over the coming weeks and progress here will be readily apparent to motorists using the
roundabout. Construction of the reinforced earth panel wall west of the Bandon Road Roundabout will get
underway before the middle of October and the first concrete pour associated with the proposed structure at
the eastern side of the Bandon Road Roundabout is also scheduled before the middle of October. It is
currently anticipated that at least some of the bridge beams on the western structure at Bandon Road
Roundabout may be in place before Christmas.
Significant earthworks are also continuing in the area south of the existing N25 between Bandon Road
Roundabout and Sarsfield Road Roundabout. Works in this area are scheduled to continue for a number of
months as part of the construction of a dedicated westbound link road parallel to the N25 mainline in this
area.
Plans for demolition of the existing footbridge at Sarsfield Road Roundabout and demolition of the existing
footbridge east of Bandon Road Roundabout are being advanced and a further update will issue under this
heading during week commencing Monday 2nd October 2011.
Earthworks in the Bandon Road Roundabout centre island will be continuing for a number of weeks and will
necessitate a number of traffic movements from the roundabout circulating carriageway into the roundabout
centre island itself. Motorists using the roundabout are asked to pay particular attention to roadwork signage
over the coming period and to take due care in relation to construction traffic in the roundabout area. Lane
closures either on the roundabout or on the roundabout approaches are not anticipated over the coming
period.
From a structures point of view the columns at the western side of the Bandon Road Roundabout will be
progressed over the coming weeks and progress here will be readily apparent to motorists using the
roundabout. Construction of the reinforced earth panel wall west of the Bandon Road Roundabout will get
underway before the middle of October and the first concrete pour associated with the proposed structure at
the eastern side of the Bandon Road Roundabout is also scheduled before the middle of October. It is
currently anticipated that at least some of the bridge beams on the western structure at Bandon Road
Roundabout may be in place before Christmas.
Significant earthworks are also continuing in the area south of the existing N25 between Bandon Road
Roundabout and Sarsfield Road Roundabout. Works in this area are scheduled to continue for a number of
months as part of the construction of a dedicated westbound link road parallel to the N25 mainline in this
area.
Plans for demolition of the existing footbridge at Sarsfield Road Roundabout and demolition of the existing
footbridge east of Bandon Road Roundabout are being advanced and a further update will issue under this
heading during week commencing Monday 2nd October 2011.
Updated: Aug 10, 2011
There are: No Comments

Rochestown Road Traffic Update

The pressure and volume of traffic on the Rochestown Road has been a cause of much gnashing of teeth and under breath comments from parents anxious to get the kids to school and commuters coming from Passage West Carrigaline.  Many have contacted me over the years complaining with due cause about the 30 min delays in getting into Douglas to work, drop the children to schools or access into City or the East and West. 

Twitter Updates